India's Reported Central Project Overrun Halved in Four Months. The Monitored List Shrank, and the Count of Late Projects Is No Longer Published

Friday, October 09, 2026

MoSPI’s flash report put the cost overrun at ₹2.88 lakh crore in August against ₹5.65 lakh crore in April, but the set fell from 1,981 to 1,731 projects, mostly roads and Railways, and the reports no longer say how many are behind schedule.

Infrastructure · Public Data · 9 October 2026

India’s Reported Central Project Overrun Halved in Four Months. The Monitored List Shrank, and the Count of Late Projects Is No Longer Published

Skip to article content
Text Size
₹5.65 → 2.88 lakh crReported cost overrun on monitored central projects, April to August 2026: a fall of about half
1,981 → 1,731Projects in the monitored set over the same months, a fall of 13%
43 of 44Projects that left the set between July and August were Railways projects
Not statedHow many projects are behind schedule; the flash reports stopped giving the count

The Ministry of Statistics and Programme Implementation publishes a monthly flash report on central government projects costing ₹150 crore or more. The latest, for August 2026, put the cumulative cost overrun at ₹2.88 lakh crore across 1,731 ongoing projects. In April the same report said ₹5.65 lakh crore across 1,981. Read quickly, the central government’s infrastructure overrun halved in four months.

It did not. The monitored set changed. Original cost across the projects fell from ₹37.12 lakh crore to ₹30.72 lakh crore in the same four months. Projects that finish, or are removed, leave the list, and their overrun leaves with them. The overrun as a share of original cost fell from 15.2% to 9.4%, but that is the share on a different set of projects. The flash report gives no list of what left, and since 2025 it no longer says how many of the remaining projects are behind schedule.

Updated 7 November 2026. MoSPI’s flash report for September 2026, released on 26 October, shows the monitored set swinging back: 1,853 projects (up 122 from August), original cost ₹34.34 lakh crore, revised cost ₹37.56 lakh crore and a cost overrun of ₹3.22 lakh crore, 9.4% of original cost. Railways projects rose from 147 to 284 and their revised cost from ₹3.14 lakh crore to ₹7.21 lakh crore, so most of the August exit has re-entered. A September column has been added to the first table. The report again gives no count of projects with overruns or delays, and MoSPI itself cautions that changes in the composition of the monitored set mean the totals do not represent fresh investment.

Half the overrun, a different set of projects

Reported cost overrun, ₹ lakh crore (projects monitored) Jan 2026 · 1,702 projects 5.52 Feb 2026 · 1,948 projects 5.66 Apr 2026 · 1,981 projects 5.65 Jun 2026 · 1,847 projects 4.93 Jul 2026 · 1,775 projects 3.41 Aug 2026 · 1,731 projects 2.88 MoSPI flash reports as reported in the press. March and May not found.
April 2026July 2026August 2026September 2026
Ongoing projects monitored1,9811,7751,7311,853
Original cost, ₹ lakh crore37.1233.7030.7234.34
Revised cost, ₹ lakh crore42.7937.1133.6037.56
Cost overrun, ₹ lakh crore5.653.412.883.22
Overrun as share of original cost15.2%10.1%9.4%9.4%
Spent so far, ₹ lakh crore20.36 (47.6% of revised cost)–16.33 (48.6%)17.73 (47.2%)
Roads ministry projects1,137–982974
Railways projects; revised cost260; –190; ₹6.38 lakh crore147; ₹3.14 lakh crore284; ₹7.21 lakh crore
Power projects; revised cost–98; ₹6.08 lakh crore102; ₹6.18 lakh crore106; ₹6.40 lakh crore
Petroleum projects; revised cost–103; ₹4.23 lakh crore117; ₹4.42 lakh crore115; ₹4.30 lakh crore

Press coverage of MoSPI’s monthly flash reports (PIB 2264967 for April, 2303115 for July, 2314852 for August, release dates from this blog’s index). The percentages and the Railways comparison are this blog’s arithmetic on those figures. The June figure of ₹4.93 lakh crore is read from a trade headline that pairs it with a revised cost of ₹40.54 lakh crore; another summary describes ₹4.93 lakh crore differently, so treat June as unconfirmed.

The ministry columns show where the set changed. Between April and August the roads ministry went from 1,137 projects to 982, a fall of 155. Railways went from 260 projects in April to 190 in July and 147 in August. Between July and August the whole set lost 44 projects and ₹3.51 lakh crore of revised cost; Railways accounts for 43 of the projects and ₹3.24 lakh crore of the cost. Power and petroleum, over the same month, gained projects.

There are three possible explanations, and the flash report does not say which applies: the projects were completed and moved to a completed list; they were merged or restated; or they were dropped from the dataset. The totals do not settle it. If the projects that left had simply been finished, most of the revised cost they carried would have been spent, and the cumulative spending on the monitored set would have fallen by about that much. Instead, revised cost fell by ₹9.2 lakh crore between April and August while recorded spending fell by ₹4.0 lakh crore, and new projects added to the set blur the comparison. Without a list of entries and exits, the fall cannot be read as progress.

The count that used to be there

What the report saidJanuary 2024March 2024August 2026
Projects monitored1,8211,8731,731
Projects with a cost overrun431449Not stated
Projects delayed780779Not stated
Cost overrun, ₹ lakh crore4.80 (18.4% of original cost)–2.88 (9.4%)

2024 figures from press coverage of the earlier reports (Deccan Chronicle, Tribune and others); the August 2026 report, per the coverage found, does not give counts of overrun or delayed projects.

Earlier reports said how many projects had overrun costs and how many were running late. In January 2024, 431 of 1,821 projects had a cost overrun and 780 were delayed, 115 of them by more than five years. After MoSPI moved to its PAIMANA monitoring portal in September 2025, the reports present projects as “ongoing” with their physical and financial progress. The Wire and ThePrint both observed that the word “delay” stopped appearing in the monthly reports after May 2025. Progress bands (in April, 391 projects at 0–20% complete and 777 at 81–100%, according to The Wire) say how much is built, not whether it is on schedule.

The reasons agencies have long given for time overruns are land acquisition, forest and environment clearances and missing support infrastructure. MoSPI has itself noted in earlier reports that agencies do not always report revised costs and dates, so the overrun figures can understate the problem.

Roads: cheap start, unfinished test

The roads ministry makes up 57% of the monitored projects, with a revised cost of ₹9.52 lakh crore. In April its overrun was only about 3% of cost, and only about 34% of its budget had been spent. Those are young projects; the test of their cost comes later. On 30 September the National Highways Authority began special quality checks on 17 projects with “abnormally low” bids: tender discount above 15%, construction cost above ₹500 crore, physical progress between 35% and 80%. First-round inspections are due by December 2026, with 39 engineers on the teams. Whether very low bids lead to more cost revisions later is the question, and the flash report cannot answer it as published.

What would fix this

  • MoSPI should put one line in every flash report: the number of ongoing projects behind their original schedule, and by how many months, as the earlier reports did, with the number that have a cost overrun beside it.
  • MoSPI should publish each month a reconciliation of the monitored set: projects added, completed, merged and dropped, with the original cost, revised cost and overrun of each group, so a fall in the total can be explained.
  • The Ministries of Railways and Road Transport and Highways should publish the final cost of every project that leaves the monitored set, against its sanctioned cost and date, so completed overruns do not vanish from the record.
  • MoSPI, with the project ministries, should publish the reasons for delay in standard categories (land, forest, environment, utilities, contracts, funding) for each late project, with the number of days pending at each agency.
  • NHAI should publish the results of the 17-project inspection, and follow those projects’ cost and time revisions, so the case for special checks on low bids is tested against what happens next.

These are proposals from this blog, not recommendations any agency has adopted.

Sources and caveats

MoSPI’s monthly flash reports on central sector infrastructure projects worth ₹150 crore and above, release dates from this blog’s PIB index (29 January 2026, PIB 2220048; 25 February, 2232712; 25 March, 2245012; 24 April, 2255270; 25 May, 2264967; 25 June, 2277758; 29 July, 2290413; 26 August, 2303115; 26 September, 2314852); PAIMANA portal release (25 March 2026, PIB 2244898); NHAI special quality checks (30 September 2026, PIB 2317061). PIB pages and the MoSPI site could not be opened from this blog’s tools, so the report figures are from press coverage (Business Standard, NBMCW, PSU Watch, DD India, Outlook Business, ETV Bharat, Policy Edge and others). Coverage gives different data months for some releases; the months used here follow the coverage, and the March and May reports were not found. The June overrun is unconfirmed (see note). July and August revised and original costs differ between summaries in places; the Railways comparison uses one summary for each month and should be checked against the reports. The 2024 figures are from press coverage of earlier reports. The observation that “delay” disappeared from the reports is from The Wire and ThePrint and has not been checked report by report; one summary of the April report’s progress bands adds to 1,941 projects against a headline of 1,981. The reasons for delay are as given by implementing agencies in earlier reports. NHAI’s selection criteria and schedule are from PTI-based coverage. This article does not claim to know why projects left the monitored set. Update of 7 November 2026: PIB 2328472, September 2026 flash report (26 October 2026); Economic Times/PTI, original and revised cost; PSU Watch.

About this article: Researched, written and edited by Umashankar Triplicane Dwarakanathan, with AI research assistance; every figure is meant to trace to the primary source cited. See the Editorial Policy for how sourcing, AI use and corrections work.

Umashankar Triplicane Dwarakanathan
Contact Us
Umashankar Triplicane Dwarakanathan
Investment Promotion & Energy-Sector Leader · Chennai, Tamil Nadu, India
LinkedIn → GitHub → Email +91 78273 81696
How this site works

Data-led analysis of India's trade, currency and industrial policy. Every article is built from primary official sources, and every figure links back to the release, table or filing it came from.

Sources. DGCI&S TradeStat (imports/exports, HSN-wise) · PIB (government press releases, January 2017 to today, refreshed daily) · RBI (circulars, balance of payments) · MoSPI (CPI/WPI, IIP) · PARIVESH (environmental clearances) · CCIL (bond yields) · BIS (policy rates) · SEBI, NSE/BSE and SEC filings for company data.

Interpretation. Figures carry their vintage and retrieval date; estimates and press-reported numbers are labelled as such; where sources disagree, both are shown. Corrections are made visibly, never silently. Articles are written with AI assistance from the cited sources — AI-generated text can misstate figures even when working from real material, so verify any number that matters to a decision against the linked primary source.

footer

Browse all articles by topic

Every piece on this blog, grouped. Or read the full index.

Agriculture & FertilisersAI ToolsChemicalsClimate & CarbonEnergy & FuelsGas & LNGImport SubstitutionIndustrial PolicyMarkets & FinanceMobility & EVPrices & InflationTextilesTrade & Tariffs

Each topic is a live archive page that updates itself as pieces are labelled. It replaces a hand-kept list that had fallen 18 articles behind.